Live Estimated Runtime

The Live Estimated Runtime (Live ERT) is the estimated runtime of the current Workflow execution.

How is Live ERT Calculated?

The Live ERT calculation is based on the ERT of individual Workflow tasks using the critical path algorithm. The result of this calculation determines the path with the longest duration in the Workflow. This is known as the Critical Path.

Workflow tasks that form the Critical Path are highlighted in Critical Path mode. To activate this mode, click the Critical Path button in the Workflow Monitor.

Reliability and Quality of Estimations

The quality of ERT data available for Workflow tasks play an important role for Live ERT estimations and Critical Path visualization.

Unexpected Critical Path courses and unlikely Live ERT estimates can occur when:

Important: For better quality Critical Path courses and Live ERT estimations, review your current executed tasks in the task details and adjust their ERT configuration if necessary.

Key Features of Live ERT

The following points outline the key features of Live ERT:

Critical Path visualization can help an operator focus on the following areas:

Notes:

The following example images display the same Workflow with and without the critical path highlighted, the feature benefits become immediately obvious:

A Workflow Displaying Critical Path

A Workflow without the critical path displayed

Important:The Critical Path visualization might behave unexpectedly for executed or heavily edited tasks.