Modifying the Status Manually

The possibility to modify the status of a task manually should be restricted to very few users. Manually changing the status of a task does not undergo any validation check. The new status is written directly to the database. This function requires a specific privilege in your user definition.

This option is not available either in Client 0 or for dynamic jobs (JOBD).

To Change the Status of a Task Manually

  1. In the Process Monitoring perspective, right-click the task and select Modify Status Manually.
  2. In the Modify Status of Task <name>, select the new status of the task.

    Important! Read the warning text in the dialog carefully.

  3. Click Modify.

Tip: Add a comment to your modification to keep track of your changes. See Adding Comments.