 Calendar Tab
 Calendar TabThe Calendar tab can be used to specify calendar conditions for a task. This task is only executed if the specified conditions apply.
This tab is also available for external dependencies.
A task that is not processed because of the specified calendar conditions obtains the status ENDED_INACTIVE - Inactive today because of calendar.
             
        
For example:
            
The task that is shown above is only executed if the workflow's activation date has been specified in the calendar FIRM.CALENDAR using the keyword ULTIMO at the workflow's activation time. 
| Field/Control | Description | 
|---|---|
| Calendar | By activating this checkbox, you can assign a calendar and calendar keywords. The following settings are available if this checkbox is active: | 
| Execute if one condition matches | The task is executed if the logical date complies with one of the specified calendar conditions. | 
| Execute if no condition matches | The task is executed if the logical date does not comply with any of the specified calendar conditions. | 
| Execute if all conditions match | The task is executed if the logical date complies with all specified calendar conditions. | 
| Use calendar definition of ext. dependency | This option is only available for external dependencies. This selection field is only displayed if the external dependency refers to a task of a different workflow. With this option being selected, the calendar settings of the external task's workflow properties are used. | 
| Table | In this table, you can select one or more calendars and calendar keywords. | 
| Calendar | Selection field for the calendar. | 
| Keyword | Selection field for the calendar keyword. It must be selected from the calendar's existing keywords. | 
The tooltips (properties) of theworkflow tasks display the usage of the Dependencies tab with a C character