Use Workday frequencies to define workdays and to schedule jobs and process flows to run on a select number of workdays from the beginning or end of the month. If you need to run a job or process flow on two workdays in the same month, create two schedules.
Using workdays, you can create schedules based on a specific day measured from the beginning or the end of the month. For example, you might want to run a task on the 5th working day of the month, or on the 4th workday from the end of the month.
Use workday schedules to run tasks on a specific day of the month
In the image above, the schedule will run SALES_REPORTS on the fourth Monday through Friday workday of each month.
Procedure
To create a workday schedule:
The ___ (st, nd, rd, th) Workday field works differently than the field used for other schedule units. It runs once a month based on this setting instead of every so many days.
If you need a job or process flow to run on more than one workday in a month, you can create several workday schedules for it. For example, if you wanted a process flow to run on the 5th and 20th workdays of each month, you would create a workday schedule for the 5th and a second workday schedule for the 20th.