Edit Jobstream - Late Criterion Tab

Each jobstream defined in AAI can be monitored during real-time execution, and the user can request that alerts be sent if the jobstream or, more specifically, when the Target Job (or Endpoint) is predicted to finish late. The user can also request an alert to be sent when the jobstream late time passes and the jobstream has not completed.

By default, a system-calculated Late Criterion is used when the jobstream is created. However, an AAI aadministrator can override that Late Criterion through the Edit Jobstream Dialog, by using either Fixed Duration (user-supplied) or End Time (user-supplied) late criteria, explained in the following sections.