Closing Release Tasks
A task can only be executed if all the previous tasks have been closed.
To Close Release Tasks
- Open the Release Planner perspective.
- Do one of the following:
From the Release Plan:
- Right-click the Task you want to close.
- Select Close.
From the My tasks tab:
- Select one task and click the Close Task icon in the toolbar (or double-click it). The Close Task dialog is displayed.
- Select the status you want to assign to the Task after closing it: Done or Failed. See: Release Task Statuses.
Note that if you close a Task with status "failed" the subsequent Task will not be executed.
Enter a comment to provide further information on the Task. (Mandatory if Task is to be closed with status "Failed")
To set one of the Tasks assigned to a group you belong to as closed, you must claim the task first. See Claiming/Revoking Release Tasks.