User Guide > Objects > Alphabetical Listing > Calendar Tab

Calendar Tab

The Calendar tab can be used to define the calendar dependencies of a task in a Schedule object. The task is only activated and executed if the specified calendar conditions are met.

A task that is not processed because of the specified calendar conditions obtains the status ENDED_INACTIVE - Inactive today because of Calendar.

For example:
The task that is shown above is only executed if its starting date is part of the WORKDAYS in the calendar FIRM.CALENDAR.

Description

Field/Control

Description

Calendar

By activating this check box, you can assign a calendar and calendar keywords.

The following settings are available if this checkbox is active:

Execute if one condition matches

The task is processed if the logical date complies with one of the specified calendar conditions.

Schedule tasks: The logical date is the start time that has been used in order to schedule them (see: Start time tab).

Execute if no condition matches.

The task is processed if the logical date does not comply with any of the specified calendar conditions.

Execute if all conditions match

The task is processed if the  logical date complies with all specified calendar conditions.

Table

In this table, you can select one or more calendars with calendar keywords.

Calendar

Selection field for the calendar.

Keyword

Selection field for the calendar keyword. It must be selected from the calendar's existing keywords.

Display in the Schedule Object and its Monitor

C is shown in the graphical display if the Calendar tab is used.